The most detail Cabrillo Unified School District provides for Measure S spending is in the annual audit report which shows $37M in spending and mentions another $11M in commitments. We have not tried to reconcile this report with the CUSD’s actual Measure S contracts and commitments which total $63.2M according to the CUSD board materials. Unfortunately the audit report does not show vendors, so it does not show that Blach Construction has received $45M from CUSD in six no bid contracts. Also the audit report would not reflect the $14.9 Cunha Building C contract since repairs haven’t started yet and the final contract has not been approved yet – CUSD will get a price from Blach Construction sometime later this year. The Board’s alternatives will presumably be accept whatever price Blach puts on the contract, or let Building C continue to rot.

Cabrillo Unified School District Measure M

Points of interest from the audit report
– CUSD has only spent $16,900 on roofing since Measure S was passed, excluding Building C repairs.
– El Granada, Farallone View, and Kings Mountain have received almost nothing from Cabrillo Unified School District Measure S other than new technology, new door locks, and new lighting that were part of districtwide upgrades.
– CUSD authorized $4M in technology spending and has spent about $3M. Details of the $4M Cabrillo Unified School District spent or committed to spending on on Technology do not appear to be publicly documented anywhere. We don’t know which vendors were used or what prices we’ve paid.

According to the contracts the Cabrillo Unified School District Board has signed, CUSD has spent or committed $63.2M from Measure S

DateCostVendorVoteDescription
2012-02-29124000Dannis Woliver KelleyCUSD signs 124,000 contract with Dannis Woliver Kelley to serve as bond counsel for Measure S
2012-02-29260000Isom Advisors CUSD signs 260,000 contract with Isom Advisors to serve as financial advisor for Measure S
2012-05-10810000Piper JaffreyConsent - 5 - 0CUSD signs 810,000 contract with Piper Jaffrey to issue Measure S bonds
2012-12-13125000Resource Solution Group5 - 0Approve Contract with Resource Solution Group to Provide Energy Audit and Related Services
2012-12-1958000Made improvements to the durability of steel substructure that supports solar panels at Half Moon Bay High School and Cunha Intermediate School.
2013-01-1786500WLC4 - 0 Kirk Riemer absentApprove a Contract With WLC Architects, Inc. to Develop a District-Wide Facility Master Plan
2013-05-0940000005 - 0 Adopt District-wide Technology Implementation Plan
2013-05-303161675 - 0Repave HMB HS Parking Lot due to solar panels
2013-10-101753049WLC5 - 0Approve Contract with WLC Architects, Inc to Design a Modernization Project for Alvin S Hatch Elementary School
2014-02-11237776WLC4 - 0 Rob Pappalardo absentApproval of a Contract with WLC Architects, Inc. to Design the New Pilarcitos High School Campus
2014-04-15234675DT Architecture5 - 0Approval of a Contract with DT Architecture, Inc. to Design a Dual Gymnasium at Cunha Intermediate School
2014-05-29508388Opening Technologies5 - 0Approve Contract with Opening Technologies, Inc. to Complete the Safe School Initiative Upgrade
2014-08-14365000WLC5 - 0Approve of a Contract with WLC Architects, Inc. to Design a Gymnasium at Cunha Intermediate School
2014-09-1879274SSA Landscape Architects5 - 0Approve a Design Contract with SSA Landscape Architects, Inc for Additional Division of State Architects Required Elements for the HMB HS Football Field Turf Replacement Project
2014-10-0953947LSA AssociatesApprove Contracts with LSA Associates, Inc. for CEQA Consulting Services for Hatch, Pilarcitos, and the Gunha Gym
2015-01-2023554SSA Landscape Architects5 - 0Approve a Master Planning and Landscape Architectured Design Services Contract with SSA Landscape Architect, Inc. for the Farallon View Play Fields and Outdoor Learning Facilities
2015-05-1493438LSA Associates4 - 0 Rob Pappalardo absentApprove a Contract with LSA Associates, Inc. for CEQA Consulting Services for the HMB High School track
2015-06-18333400Blach construction5 - 0Approve Preliminary Service Agreements with Blach Construction for Hatch and Pilarcitos
2015-06-18498659Blach construction5 - 0Approve a Lease-Lease Back Contract for Construction of the Temporary Campus for Pilarcitos High School
2015-08-134837518Blach construction5 - 0Approve a Lease-Lease Back Contract for Construction of Hatch Phase I Construction Project
2015-09-1022808Clark and Sullivan BuildersApprove Preliminary Service Agreement with Clark and Sullivan Builders, Inc for Cunha gym
2015-11-123000000Clark and Sullivan Builders5 - 0Approve a Lease-Lease Back Contract for Construction of the Cunha gym
2015-11-125261522Blach construction5 - 0Approve a Lease-Lease Back Contract for Pilarcitos
2016-06-2319773645Blach construction4 - 0 Michael Ahern absentApprove a Lease-Lease Back Contract for Construction of Hatch Phase II
2016-09-0812000 4 - 0 Michael Ahern absentApprove the Installation of a Security System at Cunha
2016-09-08975000 4 - 0 Michael Ahern absentApprove Emergency Placement of Tempoary Portables at Cunha
2017-01-1914609722Blach construction5 - 0Approve Lease-Lease Back Agreement with Blach Construction for Cunha C Building Repairs, except for waterproofing repairs
2017-04-061868837Andreini Brothers5-0Approval to Award a Contract for Half Moon Bay High School Track and Field Contract
2017-05-11172746Anderson Brule Architects5-0Approve Contract with Anderson Brule Architects Inc for rhe Repair and Recontruction of Building C at Cunha
2017-05-11632260Cal Mult Award Schedules5-0Approve Agreement for Turf Installation at Half Moon Bay High School Track and Field
2017-06-22no priceClimatech LLC3 - 0, Kimberly Hines & Kirk Riemer absentConduct a Public Hearing and Adopt Resolution No. 16-17 for Award of the Energy Performance Contract to Climatec Lighting for Hatch, Cunha, King Mountain, and lighting and heating for HMB HS
2017-09-14209623Andreini BrothersConsent 4 - 0, Kimberly Hines absentApproval of 209,622 of Change Orders/Additional Work for the Half Moon Bay High School Track Project
2017-11-0912723Andreini BrothersConsent 4 - 0, Rob Pappalardo absentApprove 12,723 Change Orders/Additional Work for the Half Moon Bay High School Track Project
2017-12-14509147CAW Architects, Inc5 - 0Approve of a Contract with CAW Architects, Inc. to Design Phase IV of Hatch Elementary School
2018-02-081329843Anderson Brule Architects5 - 0Approve Proposal for Design Cunha Building C Rehabilitation
2018-03-1463188221Grand Total Measure S Spent or Committed to Date