$27.3M in construction projects at one school (and counting) seems a little excessive when three other schools – El Granada, Farallone View, & Kings Mountain – have received almost nothing.
Date | Cost | Vendor | Vote | Description |
---|---|---|---|---|
2017-12-14 | 509147 | CAW Architects, Inc | 5 - 0 | Approve of a Contract with CAW Architects, Inc. to Design Phase IV of Hatch Elementary School |
2017-08-21 | Hatch 1-5 opens | |||
2017-06-22 | no price | Climatech LLC | 3 - 0, Kimberly Hines & Kirk Riemer absent | Conduct a Public Hearing and Adopt Resolution No. 16-17 for Award of the Energy Performance Contract to Climatec Lighting for Hatch, Cunha, King Mountain, and lighting and heating for HMB HS |
2016-06-23 | 19773645 | Blach construction | 4 - 0 Michael Ahern absent | Approve a Lease-Lease Back Contract for Construction of Hatch Phase II |
2015-12-01 | Half Moon Bay Review: “We are now officially a year late,” Yuster said when reached on Monday. | |||
2015-09-10 | Consent | Ratify the Site Lease with Blach Construction for Construction of Hatch | ||
2015-08-13 | 4837518 | Blach construction | 5 - 0 | Approve a Lease-Lease Back Contract for Construction of Hatch Phase I Construction Project |
2015-07-15 | State issues stop work order for Pilarcitos portables | |||
2015-06-18 | 333400 | Blach construction | 5 - 0 | Approve Preliminary Service Agreements with Blach Construction for Hatch and Pilarcitos |
2015-06-04 | Half Moon Bay Review: School Construction Projects Delayed | |||
2015-03-02 | 5 - 0 | Adopt Resolution No 05-15 to Admen the Initial Study and Mitigated Negative Declartation and Mitigation Monitoring and Reporting Program for the Pilarcitos and Hatch Improvement Projects | ||
2014-12-11 | 5 - 0 | Adopt Resolution No 30-14 Approving the Initial Study and Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program for the Pilarcitos and Hatch Projects, and Authorizing the Filing of the Notice Determination | ||
2014-10-09 | 53947 | LSA Associates | Approve Contracts with LSA Associates, Inc. for CEQA Consulting Services for Hatch, Pilarcitos, and the Cunha Gym | |
2014-09-25 | Half Moon Bay Review: Plan to remove trees on Cabrillo sites approved | |||
2014-09-18 | Receive a Tree Study Report and Discuss Recommendations from Kings Mountain Arbor Health and Safety | |||
2014-09-18 | 5 - 0 | Approve the Following Measure S Facility Bond Projects: Hatch, Pilarcitos, Cunha Gym, HMB HS Field and Track | ||
2013-10-10 | 1753049 | WLC | 5 - 0 | Approve Contract with WLC Architects, Inc to Design a Modernization Project for Alvin S Hatch Elementary School |
27260706 | Hatch Total |