$27.3M in construction projects at one school (and counting) seems a little excessive when three other schools – El Granada, Farallone View, & Kings Mountain – have received almost nothing.

DateCostVendorVoteDescription
2017-12-14509147CAW Architects, Inc5 - 0Approve of a Contract with CAW Architects, Inc. to Design Phase IV of Hatch Elementary School
2017-08-21Hatch 1-5 opens
2017-06-22no priceClimatech LLC3 - 0, Kimberly Hines & Kirk Riemer absentConduct a Public Hearing and Adopt Resolution No. 16-17 for Award of the Energy Performance Contract to Climatec Lighting for Hatch, Cunha, King Mountain, and lighting and heating for HMB HS
2016-06-2319773645Blach construction4 - 0 Michael Ahern absentApprove a Lease-Lease Back Contract for Construction of Hatch Phase II
2015-12-01Half Moon Bay Review: “We are now officially a year late,” Yuster said when reached on Monday.
2015-09-10Consent Ratify the Site Lease with Blach Construction for Construction of Hatch
2015-08-134837518Blach construction5 - 0Approve a Lease-Lease Back Contract for Construction of Hatch Phase I Construction Project
2015-07-15State issues stop work order for Pilarcitos portables
2015-06-18333400Blach construction5 - 0Approve Preliminary Service Agreements with Blach Construction for Hatch and Pilarcitos
2015-06-04Half Moon Bay Review: School Construction Projects Delayed
2015-03-025 - 0Adopt Resolution No 05-15 to Admen the Initial Study and Mitigated Negative Declartation and Mitigation Monitoring and Reporting Program for the Pilarcitos and Hatch Improvement Projects
2014-12-115 - 0Adopt Resolution No 30-14 Approving the Initial Study and Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program for the Pilarcitos and Hatch Projects, and Authorizing the Filing of the Notice Determination
2014-10-0953947LSA AssociatesApprove Contracts with LSA Associates, Inc. for CEQA Consulting Services for Hatch, Pilarcitos, and the Cunha Gym
2014-09-25Half Moon Bay Review: Plan to remove trees on Cabrillo sites approved
2014-09-18Receive a Tree Study Report and Discuss Recommendations from Kings Mountain Arbor Health and Safety
2014-09-185 - 0Approve the Following Measure S Facility Bond Projects: Hatch, Pilarcitos, Cunha Gym, HMB HS Field and Track
2013-10-101753049WLC5 - 0Approve Contract with WLC Architects, Inc to Design a Modernization Project for Alvin S Hatch Elementary School
27260706Hatch Total

Cabrillo Unified School District Measure S